The one-way trial of The Strand at Dee Why will be made permanent, with a sting in the tail.

At last night’s meeting of Northern Beaches Council (Tuesday, 27 June), it was decided that the ‘Streets as Shared Spaces’ trial would be made permanent. The trial, which began in August 2021, saw The Strand closed to southbound traffic, with a widened pedestrian boardwalk and separated cycleway added.

The change attracted criticism from some nearby residents, with changes to traffic patterns resulting in complaints of increased vehicle movements and congestion on nearby streets. A Council report however said that despite the congestion reported, there had been an overall decrease of 2,000 daily vehicle movements in the area.

The Strand, Dee Why

An attempt by Cr Bianca Crvelin to investigate other options, including either completely closing, or fully reversing the changes to The Strand was unsuccessful, only supported by Cr Vincent De Luca OAM and new Liberal Councillor Karina Page.

Following an initial trial period of 12 months, Council voted in April 2022 for a 12-month extension. Last night’s decision saw the trial endorsed to remain in place permanently, but with a sting in the tail for Council’s budget.

While the decision included wording to request grant funding from the NSW Government to support the installation of permanent infrastructure, it was acknowledged that such funding was ‘uncertain’.

The Strand, Dee Why

Buried in the Council papers for last night’s meeting, was the detail that the infrastructure put in place for the trial has an expected remaining life span of 2-3 years. Some complaints have been made it is already looking worn. The document reveals an estimated cost impact of $2.5m – $3m for the implementation of permanent infrastructure at the site.

“Staff have identified the potential budget of between $2,500,000 and $3,000,000 dependant on the level of finish and scope proposed,” said the document.

The Strand, Dee Why

With no funding source currently identified, that money will need to be found out of the existing capital works budget, impacting the capacity to deliver other works.

The decision came on the same night Council voted through a budget with a $3.3m black hole as a result of the NSW Government Emergency Services Levy. An additional $20m is also being spent over the next four years to replace Council’s computer system, $4.6m of which is being borrowed from a reserve fund for Mona Vale Cemetery, causing Greens Councillor Miranda Korzy to remark, ‘borrowing from the dead is unacceptable on principle’.