The Beaches Link Tunnel will be open by 2028 according to a new report.

The Environmental Impact Statement (EIS) was released for community consultation yesterday (Wednesday, 09 December) and is available as an executive summary and 29 chapters, plus 25 appendices.

Gladys Berejiklian

Gladys Berejiklian

NSW Premier Gladys Berejiklian said the project will include twin tunnels under Middle Harbour with three lanes in each direction, allowing commuters to avoid peak hour congestion on the Spit Bridge, Military Road and the Roseville Bridge.

“Beaches Link will transform the way people move to and from the Northern Beaches, bypassing 19 sets of traffic lights through The Spit, Mosman and Neutral Bay and help save up to 56 minutes between Dee Why and Sydney airport.

“Residents in Neutral Bay, Mosman and Cremorne will experience less congestion and noise, with traffic volumes expected to reduce by around a third along Spit Road.

“The Western Harbour Tunnel and Beaches Link program is expected to support around 15,000 full-time jobs,” said Premier Berejiklian.

Northern Beaches Link Tunnel
Andrew Constance

Andrew Constance

Minister for Transport and Roads Andrew Constance said the project will integrate with new and existing public transport connections.

“There will be the opportunity for new express bus services to key centres including St Leonards, Macquarie Park, North Sydney and Sydney CBD, and direct access to North Sydney to interchange with the new Sydney Metro.

“We’re also planning more than five kilometres of new cycle and pedestrian pathways, including links to the Northern Beaches Hospital precinct. This is the next stage of the consultation process, giving the community another opportunity to have its say.

“Transport for NSW has adapted its community engagement in line with current health advice regarding COVID-19, and will be providing enhanced online engagement with virtual information sessions throughout January and February.

“We’ll also work closely with locals in Balgowlah, where we’ll be returning an area equivalent to around 90 per cent of the current open space to the community. Further consultation will be held with the community on open space in Balgowlah later in 2021,” said Minister Constance.

Northern Beaches Link Tunnel depth

The tunnel will be up to 108m in depth and include new connections on the Gore Hill Freeway at Artarmon, Warringah Freeway at Cammeray, and direct access onto Burnt Bridge Creek Deviation at Balgowlah and Wakehurst Parkway at Seaforth. The Wakehurst Parkway will be widened from one lane to two in each direction between Seaforth and Frenchs Forest.

Zali Steggall

Zali Steggall

Member for Warringah Zali Steggall OAM said she welcomed the announcement from the NSW Government on the Beaches Link Tunnel.

“This is an important piece of infrastructure and the northern beaches has been desperately in need of better traffic solutions, with some of the most congested roads in NSW.

“I am concerned however that the report says no filtration is needed for the tunnel. This is purely a cost cutting decision that is short-sighted and does not account for the pollution that will be caused by the tunnel.

“Just as 20 years ago, governments thought nothing of pumping unfiltered sewerage into our oceans, now, the government thinks nothing of unfiltered stacks polluting the air for our local community,” said Ms Steggall.

Jason Falinski

Jason Falinski

Member for Mackellar Jason Falinski likewise welcomed the announcement but said the process had taken too long.

“I don’t need to tell you that if you live on the Northern Beaches, we have some of the worst roads in Australia. According to Infrastructure Australia, of the ten most congested roads in this country, three of them are on the Northern Beaches.

“In fact, if you have access to Google Maps on any Saturday or Sunday, while the rest of Sydney’s roads are green the roads coming into the Northern Beaches and on the Northern Beaches are almost always red.

“The state government, after a long delay, is releasing the environmental impact statement for the Beaches Link Tunnel. This is a project that Tony Abbott and I secured money for, and funding for. It’s been fully funded since Mike Baird was Premier, and it’s time that we got on with it.

“I want to congratulate the state government for taking this first step on a journey of a thousand miles. The project has been delayed by two years, but it is worth waiting for. The difference that this will make to people on the Northern Beaches cannot be understated,” said Mr Falinski.

Northern Beaches Link Tunnel map

The EIS reveals some key facts about the project:

  • Construction should commence in 2023 and finish in 2027
  • The road should be open to traffic in 2028
  • Standard work hours will be Mon – Fri 7.00am – 6.00pm and Sat 8.00am – 1.00pm
  • Underground tunnelling will be 24-hours, seven days per week
  • Excavated soil will be transported during standard work hours
  • Middle Harbour dredging will be during standard work hours
  • There is ‘little to no health benefit’ to installing air filtration
  • Part of Cammeray golf course will be used for construction
  • Part of Balgowlah golf course will be used for construction
  • A worksite at Flat Rock Drive, Willoughby, will impact traffic heading to Eastern Valley Way via Alpha Road
  • Olympic pool size ‘Cofferdams’ will facilitate work in Middle Harbour
  • Temporary jetties will be built at Spit West Reserve
  • A construction site will be built off Wakehurst Parkway, Seaforth, and Kirkwood Street will be closed for public access
  • The worksite at Wakehurst Parkway used for the Northern Beaches Hospital road upgrade will be reused for this project
  • Some impact expected to local traffic around construction sites
  • Travel time from Dee Why to the airport will be cut by nearly an hour
  • High noise impact to homes will be where 75+ decibels is expected. Homes impacted by high noise will have respite and alternative accommodation offered.
  • Ground noise (drilling) is expected to affect impacted homes for 1 – 2 weeks as work passes by. Eligible properties that may be affected by vibration will be offered a pre-construction property survey (highly recommended to accept).
  • 24-hour air quality monitoring in tunnels and at ventilation outlets with data publicly available
  • Ambient air quality monitoring 12 months prior and two years after completion
  • 77 non-Aboriginal heritage sites identified in the work area
  • 11 Aboriginal heritage sites identified within the work area
  • Most of the work area has been disturbed or contains non-native plants
  • Two threatened flora species were identified within the work area
  • Six threatened fauna species were identified within the work area
  • Endangered Little Penguins are known to visit the work area
  • 11 threatened marine species are known or likely to be in the work area
  • Two threatened marine ecologies were identified within the work area
  • 90 percent of the space used at Balgowlah will be returned
  • 4,000sqm of additional land will be added to Manly Dam Reserve
  • Seabed dredging will use a method safe for sensitive marine ecologies
  • Land for tunnels will be acquired via ‘subsurface acquisition’. Properties affected by ‘subsurface acquisition’ can still build a pool or basement garage.
  • Tunnelling will create approximately three million cubic metres of fill

The most useful document for most people will be the Guide to the EIS, which is a 128-page summary document outlining the major aspects of the EIS, including:

  • An overview of the project scope
  • Key benefits of the project
  • Consultation inputs to the reference design
  • Entry and exit point designs
  • Tunnel depths at various points
  • How construction will be done
  • Entry and exit points
  • Locations of worksites
  • Working in Middle Harbour
  • Traffic and transport assessment
  • Noise and vibration assessment
  • Air quality and human health assessment
  • Heritage assessment
  • Urban design and visual amenity assessment
  • Biodiversity assessment
  • Underwater construction techniques
  • Consultation and making a submission

Submissions can be made until Monday, 01 March 2021, via the project website or by post. Anyone making a submission must also declare any political donations in the previous two years.

Images: Transport for NSW